The long run ticket counter at JFK’s new Terminal 1.
Leslie Josephs/CNBC
It is from completed however the brand new, $9.5 billion Terminal 1 at John F. Kennedy Worldwide Airport is taking form. Its first part is slated to open in mid-2026.
It is going to change the present terminal, which opened in 1998.
The terminal, which will likely be JFK’s largest, is now weathertight. Winding baggage conveyor belt buildings have been put in, and you may make out future ticket counters, the place prospects flying carriers like Turkish Airways, Air New Zealand, Etihad Airways, Air China, Taiwan’s China Airways and others will set down their baggage and present their passports to ticket brokers.
JFK’s new Terminal 1 underneath development.
Leslie Josephs/CNBC
The terminal — set to be roughly the dimensions of the 2 new LaGuardia Airport terminals that opened previously decade mixed — will likely be devoted solely to worldwide vacationers, which the builders stated is essential to the design.
“From the very first pen to paper … we had the worldwide buyer in thoughts,” Jennifer Aument, CEO of the New Terminal One, the corporate growing the mission, stated at a press convention on the airport final month.
The brand new baggage transport system at JFK’s new Terminal 1.
Leslie Josephs/CNBC
CNBC and different media obtained a take a look at the development progress, led by Aument, in early July as a part of what the corporate stated will doubtless be among the many final hardhat excursions of the ability earlier than opening day.
The mission is a part of the Port Authority of New York and New Jersey’s $19 billion overhaul of JFK. Along with Terminal 1, the present Terminal 7, at the moment dwelling to Alaska Airways and Eire’s Aer Lingus, will likely be knocked down for a brand new Terminal 6, whose first gates are set to open subsequent 12 months. LaGuardia Airport’s revamp, as compared, was about $8 billion.
As air site visitors grows, airports across the nation are racing to interchange getting older infrastructure.
U.S. airports want a minimum of $173.9 billion for infrastructure upgrades from this 12 months by way of 2029, in accordance with a report earlier this 12 months by the Airport Council Worldwide-North America.
“These investments – averaging almost $35 billion yearly – are important to accommodate airways and passengers, enhance operational effectivity, elevate service high quality and buyer expertise, and fulfill airport resiliency wants,” it stated.
The long run baggage declare space at JFK’s new Terminal 1.
Leslie Josephs/CNBC
The brand new JFK Terminal 1 is ready to open across the begin of the 2026 World Cup, when some video games will likely be held at MetLife Stadium in East Rutherford, New Jersey, about 30 miles away.
Greater than half of the airways at JFK are altering terminals within the coming years due to the development, Aument stated.
One factor she pointed to with the brand new design: “a terminal flooded with mild.” Meaning no basement customs strains.
JFK’s Terminal 1’s new departure corridor underneath development.
Leslie Josephs/CNBC
The departures corridor, safety lanes and customs will likely be on the identical stage of the three-floor terminal, which encompasses a wall of slanted home windows. Its design, led by structure agency Gensler, is meant to conjure the picture of a butterfly, with the physique splitting the terminal down the center.
The AirTrain, which connects the airport’s terminals and parking tons with practice stations in Queens, is already working by way of the development web site and can cease on the terminal when the ability opens.
JFK’s overhaul additionally consists of roadway enhancements across the airport, the place site visitors has crawled across the largest hub within the area for years.
JFK’s future Terminal One underneath development
Leslie Josephs/CNBC
Terminal 1’s mid-2026 open will embrace the departure and arrival areas and the primary 14 gates, all able to receiving wide-body plane which are used for long-haul flights, and could have a capability for 14 million passengers a 12 months.
There will likely be 23 gates — 22 wide-body gates and one narrow-body gate — for planes like an Airbus A320 or a Boeing 737s — when the remainder of the mission is full, at the moment scheduled for 2030.
The ultimate model of Terminal 1 may also have greater than 300,000 sq. ft of eating, retail, lounge and leisure house, with greater than half, 180,000 sq. ft, only for retail and eating.
The long run entrance of JFK’s new Terminal 1.
Leslie Josephs/CNBC
Aument stated the airport would be the just one within the U.S. with a cash-and-carry duty-free procuring. Typically, prospects will make duty-free purchases which are then returned to them earlier than they board their flights, however on this format, they will take them instantly.
The brand new terminal may also have its personal microgrid, with photo voltaic panels on the roof, that the developer stated will allow the ability to have “full resiliency and upkeep of 100% [of the terminal’s] operations within the occasion of energy disruptions.”