A newly constructed rail overbridge (ROB) in Bhopal, which made headlines for its virtually 90-degree flip, has shortly gone from being the topic of memes to the topic of an investigation. And, as an enquiry will get underway to determine what led to the peculiar development, officers from the Madhya Pradesh Public Works Division (PWD) and the Indian Railways look like shifting blame.
The 648-metre bridge within the Aishbagh space, which price Rs 18 crore to construct, was meant to get rid of lengthy delays at railway crossings and shorten the commute for almost three lakh individuals each day.
KPS Rana, the engineer-in-chief of the PWD, advised The Indian Categorical that the bridge’s design was sanctioned in 2018 and was executed by a workforce initially from the bridge engineering division, comprising officers on the assistant engineer, superintendent engineer, govt engineer, and chief engineer ranges.
“We now have shaped a committee to look into the position of those officers,” he stated. Rana emphasised that the Basic Association Drawing (GAD), a complete format plan vital for all ROB tasks, was ready in collaboration with the Indian Railways and supervised throughout the PWD by the Chief Engineer (Bridges). G P Verma, the Chief Engineer (Bridges), refused to touch upon the matter.
Rana stated the “closing approval” remained throughout the division of the Chief Engineer (Bridges), and “the design didn’t escalate to larger authorities.”
“It was the bridge engineering division which had handled the design. The GAD was formulated with the assistance of railway officers and PWD officers. A non-public contractor was engaged to execute the work, they usually even have a closing position to execute the design within the later levels. If there had been higher communication, we may have rectified the design or made an underbridge. The railway constructed its personal ROB contemplating the house crunch,” he stated.
Rana stated the venture confronted spatial constraints, and the difficulty of alignment ought to have been flagged earlier within the GAD formulation part.
Story continues under this advert
“There was an absence of communication between completely different departments over this. If we may have gotten this on the reception stage itself, the Railways may have denied giving approval to the venture. Then we may have labored on a redesign,” he stated.
And so, the departments proceeded with the prevailing design, and options akin to an underground crossing or completely different alignment weren’t explored, Rana stated.
Railways spokesperson Naval Agarwal acknowledged that each departments had coordinated through the design part and that Railways had raised early considerations in regards to the alignment. “We had executed our job and constructed our portion of the ROB as per the GAD. We had communicated to the PWD by way of a letter a while in the past on the design flaws. We did our job.”
Anupam Awasthi, the Chief Challenge Supervisor, declined to remark intimately, stating solely that he was not concerned when the GAD was ready and suggesting that any design flaws may have been addressed through a revision proposal at the moment. “If there was an method downside, then there may have been a revision proposal. That was not executed,” he stated.
Story continues under this advert
The development contract was awarded to M/s Puneet Chadha, a personal agency based mostly in Bhopal. Senior construction engineer Kailash Kushwaha, who labored on-site for 2 years, supervising a workforce of 60 individuals, stated the design got here instantly from the PWD. He stated that the bridge was constrained on one facet by metro development and on the opposite by an electrified railway line, limiting accessible house.
He stated they labored with the Chief Engineer (Bridges). “The PwD had raised these problems with lack of house; it’s primarily the railway division’s fault that they didn’t coordinate with us,” Kushwaha alleged.
The PWD has constituted a four-member committee, together with two chief engineers and an govt engineer, on the orders of PWD Minister Rakesh Singh. This committee will assess the design, consider accountability, and advocate corrective measures. The protection measures into account embrace set up of velocity breakers at 5 places, mirrors for visibility on the 90-degree flip, reflective radium strips, velocity restrict signage, 20 new streetlights on the bridge, and widening the curve utilizing girders on the triangle base of the ROB.